FG tackling challenges of relocation of services, compensations slowing down Lagos-Ibadan Expressway project

FG tackling challenges of relocation of services, compensations slowing down Lagos-Ibadan Expressway project
.entry-header –>

The Federal Government on Wednesday said that it was dealing with the challenges of compensations payment and relocation of services slowing down Lagos-Ibadan Expressway rehabilitation and reconstruction project.

between content ad –>

Alhaji Babangida Hussaini, Permanent Secretary, Federal Ministry of Works and Housing, made the remarks during a technical inspection of roads in Lagos and added that the speed of work on the project was impressive except the challenges.

He assured Nigerians that the project would be delivered on schedule in December 2022.

“Overall the progress of work is impressive, actually, let me just say that part of the challenges we are having are compensation issues, and also the relocation of existing utilities. This is what is slowing us down and this is why I am here.

“And I can see that we have to really work fast to match the progress of work but overall the project is moving at the right pace and we hope it should be completed on schedule,’’ he said.

He explained that about twenty owners of properties demolished for the construction of an interchange bridge at Lotto axis of the Lagos Ibadan expressway, are yet to be compensated by the federal government.

Hussaini said the compensation would be paid after completion of the survey and other due diligence, adding that, work on that section was “one of the very critical ones on the Lagos – Sagamu stretch of the Expressway’’.

Vanguard News Nigeria

.entry-content –>

All rights reserved. This material and any other digital content on this platform may not be reproduced, published, broadcast, written or distributed in full or in part, without written permission from VANGUARD NEWS.



Read the full article at www.vanguardngr.com

More

Leave a Reply

Your email address will not be published. Required fields are marked *

FG tackling challenges of relocation of services, compensations slowing down Lagos-Ibadan Expressway project

 

Log In

Or with username:

Forgot password?

Forgot password?

Enter your account data and we will send you a link to reset your password.

Your password reset link appears to be invalid or expired.

Log in

Privacy Policy

Add to Collection

No Collections

Here you'll find all collections you've created before.