The Transmission Company of Nigeria (TCN) on Tuesday announced the restoration of bulk power supply through the Ahoada-Yenagoa 132kV transmission line.
The TCN General Manager, Public Affairs, Ndidi Mbah, in a statement on Tuesday, said the restoration was achieved on 30 November.
Ms Mbah said this follows the successful reconstruction of collapsed towers and restringing of vandalised conductors by TCN contractors.
“The Transmission Company of Nigeria (TCN) announces the restoration of bulk power supply through the Ahoada-Yenagoa 132kV transmission line at 08:03 hours on 30 November 2024,” she said.
Earlier in August, the TCN said two transmission towers, T98 and T99, along the Ahoada/Yenagoa 132kV line in the Igbooghene community of Bayelsa, were destroyed by vandals.
At the time, the TCN said the incident caused the collapse of both towers, cutting off the power supply to Bayelsa, including its Yenagoa Substation and the Gbarain Power Station.
On Tuesday, Ms Mbah…