The Federal Government has indefinitely suspended construction of a pedestrian bridge at Aseese on the Lagos-Ibadan Expressway, after a traffic diversion caused a gridlock that left motorists stranded for more than 20 hours.

The Federal Government has suspended construction of a pedestrian bridge at Aseese on the Lagos-Ibadan Expressway, after a gridlock left motorists stranded for more than 20 hours.

The Federal Ministry of Works and CBC Construction Company had planned to carry out the work from Wednesday, November 18, to Sunday, November 22. To make room for it, inbound Lagos traffic was diverted at Aseese, opposite Christ Embassy. The diversion caused a jam that started around 2pm on Wednesday and lasted until about noon on Thursday.

Many motorists left their vehicles and walked several kilometres home. Commercial drivers raised the Mowe-to-Berger fare to as much as ₦3,000, up from the usual ₦700 to ₦800, and motorcyclists charged up to ₦5,000 for the same trip.

President Bola Tinubu’s media adviser, Sunday Dare, was stuck in the traffic for more than five hours. He questioned why the contractor worked during peak hours instead of at night, calling it “unnecessary pain.”

Babatunde Akinbiyi, spokesperson for the Ogun State Traffic Compliance and Enforcement Agency (TRACE), said the diversion has been suspended until further notice, and the agency apologised to road users. Richard Adeleye, acting Controller of Works in Ogun State, confirmed that the traffic situation led to the suspension.

Commuters have called on the Ogun State Government to repair inner roads so motorists have alternative routes. They also want the Federal Government to monitor contractors working on busy corridors more closely.